We have received the following update from Latrobe City re the progress of the playground.
- The path that links Narracan Drive to the existing path network was marked out last week by contractors.
- Temporary fencing will be installed at the site next Monday, with signage detailing the project and LVA funding etc.
- The path construction as well as some site stripping and soil spreading will commence next week on site.
- Procurement is complete for all equipment. Latrobe City are now working with the suppliers on timeframes for installation.
Reminder to members:
We are still chasing up where we can obtain rail cogs from. If anyone has any suggestions, please let Maureen know as soon as possible.